| June 15, 2005 |
Arvada Library groundbreaking |
 |
| July 15, 2005 |
Design review committee recommends approval of library design |
 |
| July 20, 2005 |
Temporary fence installed around the former Ashton building |
 |
| August 15-17, 2005 |
Demolition of former Ashton building |
 |
| August 19-22, 2005 |
Temporary construction fence around Olde Town Square extended so that the area can be used for staging of shoring materials |
 |
| August 23 - November 1, 2005 |
Shoring installation, basement excavation, and foundation and basement-wall construction under way |
 |
| August 23 - September 30, 2005 |
Construction truck traffic at its highest levels, equating to approximately 20 trucks per day. |
 |
| November 2005 - February 2006 |
Structural steel, floor decks and concrete floors installed. |
 |
| January - April 2006 |
Plumbing, HVAC and electrical installation. |
 |
| February - April 2006 |
Roof, brick exterior, curtainwalls, storefronts and elevators installed. |
 |
| April - August 2006 |
Interior construction takes place. |
 |
| May - July 2006 |
Complete plumbing, HVAC and electrical systems. |
 |
| June 2006 |
Renovation of the Olde Town Square begins. |
 |
| August 2006 |
Library construction scheduled for completion. |
 |
| August 2006 - September 2006 |
Furniture and equipment installation |
 |
| September 2006 |
Books and materials moved from existing library to new building. |
 |
September 14, 2006
|
Parking lot complete.
|
 |
September 16, 2006
|
New library opens.
|
 |
October 2006
|
Rennovation of the Olde Town Square completed.
|
 |